E1 New employment on identified sites
The development of land for employment purposes
(Classes B1/B8 of the Town and Country Planning (Use Classes)
Order 1987) is proposed on the sites identified in Table 3 below,
as numbered on the Proposals Map. Development proposals for each
of these sites will need to have regard to the relevant footnote(s)
in the table. Proposals for the larger sites (over 2ha) will
need to include measures for the provision of sustainable transport
(travel plans), landscaping and environmental improvements as
an integral part of the development scheme and as further detailed
in policies A-D below. Class B2 uses may be appropriate subject
to environmental and amenity considerations except on proposals
sites E1, 2, 3 and 19 where only B1 uses will be permitted.
Proposals for the use of allocated sites for
non-employment uses will be determined on the basis of Policy
E6 (Retention of employment land and buildings).
Table 3: Employment Policy E1 - New employment
on identified sites
|
Site name
|
Notes
|
Hectares
|
Acres
|
|
TORQUAY
|
|
|
|
(1)
|
Kerswell Gardens
|
See Policy E1.1(A)
|
2.20
|
5.4
|
(2)
|
Riviera Way South
|
See Policy E1.2(B)
|
4.9
|
12.1
|
(3)
|
Riviera Way North
|
ACS
|
{2.0}
|
{4.9}
|
(4)
|
Browns Bridge Road
|
A+
|
1.4
|
3.5
|
(5)
|
Lummaton Quarry
|
DFS
|
{1.8}
|
{4.4}
|
(6)
|
Site of MFI, Teignmouth Road
|
W+
|
0.5
|
1.2
|
(7)
|
Lymington Road Car Park
|
AEH TM+
|
0.45
|
1.1
|
(8)
|
Site of Magistrate's Court, Union Street
|
E TM S
|
{0.1}
|
{0.3}
|
(9)
|
Temperance Street
|
E TM S
|
0.2
|
0.5
|
(10)
|
Site of former Royal Garage, Torwood Street
|
E TM
|
0.5
|
1.2
|
(11)
|
Torwood Street / Torwood Gardens
|
E TM
|
0.15
|
0.4
|
|
Torquay Sub Total
|
|
10.3
|
25.5
|
|
PAIGNTON
|
|
|
|
(12)
|
Dendy Road
|
E TM
|
0.27
|
0.7
|
(13)
|
Station lane
|
EH TM S
|
0.42
|
1.0
|
(14)
|
North of Tor Park Road
|
S
|
{1.65}
|
{4.1}
|
(15)
|
Tor Park Road Extension
|
S
|
{0.3}
|
{0.7}
|
(16)
|
Yalberton Road
|
See Policy E1.16(C)
|
16.6
|
41.0
|
(17)
|
Long Road
|
ABS+
|
{5.9}
|
{14.6}
|
(18)
|
Kemmings Way
|
-
|
{0.4}
|
{1.0}
|
(19)
|
Long Road South
|
See Policy E1.19(D)
|
11.44
|
28.3
|
|
Paignton Sub Total
|
|
28.73
|
71.0
|
|
BRIXHAM
|
|
|
|
(20)
|
South of Oxen Cove
|
G
|
0.45
|
1.1
|
|
Brixham Sub Total
|
|
0.45
|
1.1
|
|
TOTAL NEW EMPLOYMENT SITES
|
|
39.48
|
97.6
|
Notes:
A These sites are high profile locations where high quality,
well-landscaped development will be required. Class B1 uses (in
particular offices and high tech) are appropriate
B Planning Brief required
C Business Park sites
D General industry use (Class B2 may be particularly appropriate
on these sites, subject to environmental considerations)
E Office sites
F Site is an SSSI, which must be protected (see Policy NC2 Protected
sites - nationally important sites)
G Subject to Environmental Impact Assessment
H Subject to review of parking requirements in context of Torquay
Central Area Transportation Strategy
S These sites have been identified by the Environment Agency
as requiring care to avoid flooding. Where possible, sustainable
drainage measures should be employed (see Policy EP11 Flood control)
TM Town centre site suitable for mixed use development (see
Policy S2 Town centre mixed use developments)
Explanation:
4.56 Employment provision at the level identified is considered
essential to:-
(a) meet the needs of Torbay’s population, which has
a high rate of unemployment;
(b) to broaden Torbay’s economic base; and
(c) to enable the Council to benefit from Assisted Area and
EU funding (see paragraphs 4.23 and 4.26).
4.57 The Devon Structure Plan makes provision for the development
of 70 hectares of new employment land during the Plan period.
Local Plan employment land provision currently falls short of
this Structure Plan target. As part of this total, 39.48 hectares
are identified on the large sites listed in Policy E1,
with the balance to be made up by development on Business Investment
Areas (Policy E3) and Small Business Areas (Policy
E4), in addition to yields from existing and possible
future windfall consents arising from Policy E5.
(See Figure 23 and paragraph 4.40, which also outlines the Council’s
intentions to monitor employment land take up).
4.58 The Local Plan provides a wide range of sites for
new industries/offices. This range is essential to provide alternative
employment opportunities for the high level of unemployed in
the area. In any event, proposals will be expected to comply
with landscape, nature conservation and environmental protection
policies of the Local Plan. In this respect, structural landscaping
belts are identified on the Proposals Map for key sites which
require particularly careful treatment.
4.59 It is important to broaden Torbay’s employment
base and to attract investment from the growth sectors, including
office, research and new technology uses. In particular, there
is an identified need for a high quality business park which
will attract prestige users. Business parks require a well-landscaped
campus-style format. They must also be of a sufficient size and
relationship to other employment areas to achieve a critical
mass. These developments require high quality uses; general industry
will not be appropriate, nor will light industrial or warehousing
uses which fail to meet the above criteria.
4.60 In the context of the Halcrow Fox Western Corridor
Study, the development of these sites is likely to require substantial
input by developers to sustainable transport measures in the
locality. Travel plans are therefore likely to be an important
consideration in determining proposals for these sites.
4.61 In view of their strategic importance and visual sensitivity,
detailed policies have been prepared for four key employment
sites, namely Kerswell Gardens [E1.1(A)], Riviera
Way South [E1.2(B)], Yalberton Road [E1.16(C)] and
Long Road South [E1.19(D)]. Individual Planning
Briefs will be prepared for these sites and will set out the
following:-
(a) details of the main pedestrian circulation, cycle routes
and public transport links;
(b) road and junction layouts, parking provision and layout
of car parks;
(c) details of flood control and sustainable drainage measures;
(d) the general provision of infrastructure;
(e) guidance on the design and built form, including footprints,
size and height of buildings, massing, roofscape, materials
and colours, and advertising;
(f) archaeological assessment within the envelope of the proposed
development; and
(g) details of the phasing of the proposed development, in
the context of the overall scheme.
The Briefs will also set out detailed requirements for any development
proposal to meet the provisions of Policies E1.1(A), E1.2(B), E1.16(C) and E1.19(D).
4.62 Flood prevention measures may also be necessary for
developments on several proposed employment sites. These are
identified in the table of sites forming part of Policy
E1.
4.63 Policy E1.20 is part of a range of
projects of land reclamation and harbour improvements at Brixham
Harbour. These will need to be the subject of an environmental
impact assessment to ensure that schemes do not unduly harm the
environment including inter-tidal habitats.
4.64 The majority of uses on land allocated for employment
use should be within Class B1 or B8 of the Town and Country Planning
(Use Classes) Order 1987. On certain sites, particularly those
located in town centres, scope may exist for the introduction
of small workshops forming part of mixed-use developments. In
exceptional cases it may be appropriate to allow non-industrial
uses where these contribute to the viability of an employment
scheme. Such uses should be subordinate to the industrial use
of the site and applicants must demonstrate that the use would
not harm other interests of acknowledged importance.
4.65 General industry (Class B2 in the Use Classes Order)
is not appropriate within or adjacent to residential areas. It
can also adversely affect the environment of certain light industrial
or commercial areas, especially those with clean air requirements.
However, certain Class B2 uses can operate on industrial sites
without causing harm to adjoining occupiers, and may be more
appropriately located on industrial estates rather than in residential
areas. Before allowing applications for such use, the Council
will wish to be satisfied that the proposal would not cause harm
to nearby occupiers or the character and appearance of the area.
4.66 Scope exists for general industrial development at
Lummaton Quarry (Policy E1.5). Whilst the reclaimed floor level
of the quarry is not visible from residential areas to the east
of Happaway Road, it is accepted that some uses falling within
Use Class B2 would not be acceptable because the quarry is situated
in close proximity to these areas. Any B2 permission will therefore
be limited to individual users and will be subject to strict
environmental control in order to ensure acceptable noise and
odour levels. Any development at Lummaton Quarry should also
have regard to the existence of the Site of Special Scientific
Interest at this location and should ensure that there is no
adverse effect on the quarry face, and that satisfactory access
to the quarry faces is retained for geological purposes (see Policy
NC2).
4.67 The Lymington Road Car Park, Torquay site (E1.7)
is allocated primarily for office use. However, the existing
car park makes an important contribution to town centre car parking
provision and any development of this site should be considered
in the wider context of the Torquay Central Area Transportation
Strategy outlined in the Council’s Local Transport Plan.
The location is also suitable as a town centre mixed use site
in Policy S2 (TM1), which outlines possible
suitable additional uses.
4.68 The Long Road, Paignton site (E1.17),
is situated in an environmentally sensitive location. This is
particularly the case in respect of the section of this allocation
that lies on the northern side of Long Road. The planning brief
required for this site will need to provide guidance on the design
and built form of proposed development, access and car parking,
provision of infrastructure and flood control and sustainable
drainage. The issues of strategic landscaping, height of buildings
and colour of building materials will require particularly careful
attention.
4.69 Where tipping is required to bring land into use,
adequate gas venting measures shall be provided where necessary.
E1.1(A) Kerswell Gardens, Torquay
The development of a business park at Kerswell
Gardens, Torquay (2.20 hectares net) is proposed. The following
policy requirements will apply:-
(1) the development should be restricted to
B1 uses under the Use Classes Order, although limited ancillary
B8 uses may be acceptable. B2 uses will not be acceptable;
(2) the development should reflect the high
profile of the site at a major gateway to Torbay while also
responding to the character and scale of the setting. A high
quality development is sought;
(3) appropriate flood alleviation measures
should be implemented in the context of Policy EP11;
(4) appropriate archaeological assessment should
be implemented in the context of Policy BE9;
(5) the valley sides outside the site will
be safeguarded from development in view of their visual prominence
in the context of the wider landscape setting;
(6) a framework of strategic landscaping should
be established as an integral part of the development, in accordance
with Policy L10;
(7) the proposed development should demonstrate
the importance of the planting, retention and management of
trees in the context of Policy L9;
(8) measures for the protection of the existing
landscape framework should be included, pursuant to Policy
L8;
(9) the impact on areas of ecological importance
should be minimised, consistent with Policies NCS and NC5;
(10) arrangements for access to the site should
be subject to a Transportation Assessment (TA) which clearly
sets out sustainable transport solutions for all means of travel,
including pedestrians, cyclists and public transport. Vehicular
access to serve the development should be taken from a new
road junction on Torquay Road which should be designed to accommodate
the junction arrangements required for the proposed A380 Kingskerswell
Bypass (see Policy T21). Off-site highway improvements will
therefore be required;
(11) access arrangements should be designed
to avoid a materially adverse impact on both the local and
major road network of additional traffic generated by the development,
having due regard to the proximity of the site to the primary
access road into Torbay; and
(12) any proposal for the development of the
site will be required to ensure that the site is developed
in a comprehensive manner in accordance with the principles
set out in a planning brief.
Explanation:
4.70 Kerswell Gardens is below the minimum size to be a
viable ‘business park’ on its own. However, it is
intended to be a well-designed ‘high tech’ site enjoying
the advantages of proximity to Riviera Way South (E1.2)
with good transport links. Both sites are in prominent locations
and landscaping/nature conservation measures are essential. In
addition, it may be necessary to provide flood protection measures
to prevent flooding in the Teignbridge District area. Access
onto the road network will also require careful planning. A Planning
Brief will be required to guide development on this site, as
highlighted in paragraph 4.61 above.
E1.2(B) Riviera Way South, Torquay
The development of a business park at Riviera
Way South, Torquay (4.9 hectares net) is proposed. The following
policy requirements will apply:-
(1) the development should be restricted to
B1 uses under the Use Classes Order, although limited ancillary
B8 uses may be acceptable; B2 uses will not be acceptable;
(2) the development should reflect the high
profile of the site at a major gateway to Torbay while also
responding to the character and scale of the setting; a high
quality development is sought;
(3) pursuant to Policy BE11, development on
the site should minimise impact upon Edginswell hamlet;
(4) appropriate flood alleviation measures
should be implemented in the context of Policy EP11;
(5) appropriate archaeological assessment should
be implemented in the context of Policy BE9;
(6) a framework of strategic landscaping should
be established as an integral part of the development, in accordance
with Policy L10;
(7) the proposed development should demonstrate
the importance of the planting, retention and management of
trees in the context of Policy L9;
(8) measures for the protection of the existing
landscape framework should be included, pursuant to Policy
L8;
(9) the impact on areas of ecological importance,
including the Local Wildlife Sites, should be minimised, consistent
with Policies NCS and NC5;
(10) arrangements for access to the site should
be subject to a Transportation Assessment (TA) which clearly
sets out sustainable transport solutions for all means of travel,
including pedestrians, cyclists and public transport; vehicular
access should be taken from a new road junction on Newton Road
to the east of the site; off-site highway improvements will
therefore be required;
(11) access arrangements should be designed
to avoid a materially adverse impact on both the local and
major road network of additional traffic generated by the development,
having due regard to the proximity of the site to the primary
access road into Torbay; and
(12) any proposal for the development of the
site will be required to ensure that the site is developed
in a comprehensive manner in accordance with the principles
set out in a planning brief.
Explanation:
4.71 Riviera Way South is below the minimum size to be
a viable ‘business park’ on its own. However, it
is intended to be a well-designed ‘high tech’ site
enjoying the advantages of proximity to Kerswell Gardens (Policy
E1.1) with good transport links. Both sites are in prominent
locations and landscaping/ nature conservation measures are essential.
In addition, it may be necessary to provide flood protection
measures to prevent flooding in the Teignbridge District area.
Access onto the road network will also require careful planning.
4.72 A Planning Brief for the Riviera Way South site will
be prepared in accordance with the principles highlighted in
paragraph 4.61 above.
|